Sr.No. | Components | Target | Achivement | % |
---|---|---|---|---|
1 | 2 | 3 | 4 | 5 |
1 | Tubewell | 89 | 87 | 97.75 |
2 | Pump House | 89 | 86 | 96.63 |
3 | Chlorination system | 61 | 61 | 100.00 |
4 | OHT | 83 | 81/68 | 97.59 |
5 | Distribution (Line Laying in Km.) | 699 | 681 | 97.42 |
6 | Solar Plant | 81 | 70 | 86.42 |
7 | F.H.T.C. | 45453 | 43889 | 96.56 |
9 | ROAD DISMENTLING/RESTORATION(KM) | 663 | 651 | 98.19 |
10 | Villages where 100 % road restoration completed | 97064 | 59914 | 61.73 |
11 | Comissioning of Village | 91 | 65 | 71.43 |
12 | Regular water supply | 91 | 61 | 67.03 |
Sr.No. | Agency | No Of Scheme | No Of Village | households | FHTC | FHTC % | Har Gar Gal | Certified |
---|---|---|---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
1 | LC INFRA | 85 | 91 | 38701 | 37375 | 96.57% | 34 | 12 |
Total | 85 | 91 | 38701 | 37375 | 96.57% | 34 | 12 |